Skip to main content

Sewer Pipeline & Manhole Rehabilitation

Somerville’s over 180 miles of sewer pipelines are a critical asset to our community that residents and businesses rely upon daily. Just like any other infrastructure or equipment, our sewers require regular upkeep and rehabilitation in order to function effectively. 

Each year the City’s Department of Infrastructure and Asset Management sets out to repair deficiencies identified in the previous year’s Annual Sewer and Storm Drain Inspection Program

View of list of streets where repairs will be taking place in 2024 here.

 Español, Português, Kreyòl Ayisyen, नेपाली, 简体中文版, 繁體中文版.

Active Work 

Scheduled and Locations of Work

Remaining Work- Remainder of Fall '24

  • Crews will be returning to the streets where work took place earlier to complete remaining minor items. This work should last no longer than a few hours to one day in any particularly location and will not affect residents' sewer service.

Construction Impacts: 

  • CIPP Lining Only - Affected residences are asked to limit their water usage during work hours on the date when work is taking place on the stretch where their home located 
    • affected residents will receive a secondary flyer with more information this request approximately 24 hour prior to work on their street
  • On-street parking will be restricted during construction.
    • Please observe posted signage.
  • Periodic road closures may be required.
    • Access will be maintained for pedestrians/residents  
  • Trash/recycling pick-ups and deliveries will not be affected.

If you have questions, please email construction@somervillema.gov or call the Engineering Division at (617) 625-6600 x 5400

How It Works

Each year the City inspects a portion of our sewer and drainage system to identify areas in need of rehabilitation. While more critical issues are addressed via emergency repairs, regular rehab and maintenance typically takes place the following year through our Sewer Pipeline and Manhole Rehabilitation Program.

Pipelines and manholes are rehabilitated using a combination of methods, including but not limited to the following: 

  • Injection Grouting – acrylic grout is pressure injected through a defect in the pipe, forming an impermeable barrier
  • Cured In Place Pipe (CIPP) Lining – a flexible liner is inserted inside the existing pipe, inflated, and then hardened, forming a smooth surface inside the existing pipe
  • Open Trench Excavation – crews will dig down to and expose existing pipe, remove the defective section or full length of pipe, and then install new pipe
  • Spot Repair – similar to Open Trench Excavation, crews will dig a small trench, remove a short section of pipe, and install a new section of pipe
  • Manhole Lining & Sealing – epoxy or cementitious material is applied to the inside of the manhole as a coating, restoring structural integrity and waterproofing the manhole


When excavation is required for construction, City contractors will pave the impacted area with a temporary course of asphalt immediately following the work. They will then return roughly a year later and perform final surface restoration.
 

Affected Streets 2024

Work is scheduled to occur on portions of the following streets:
 

Street Status Street Status
Bailey Street Complete August 2024 Hillsdale Road Excavated Work Complete, Trenchless Scheduled for Week of 9/2
Belknap Street Complete August 2024 Hooker Avenue Trenchless Scheduled for Week of 9/9
Broadway Excavated Work Complete, Trenchless Scheduled for Week of 9/9 North Street Excavated Work Complete, Trenchless Scheduled for Week of 9/16
Chetwynd Road Excavated Work Ongoing, Trenchless Scheduled for Week of 9/9 Powder House Boulevard Excavated Work Complete, Trenchless Resumes September 2024
Conwell Avenue Excavated Work Complete, Trenchless Work Complete Raymond Avenue Excavated Work Complete, Trenchless Scheduled for Week of 9/2
Crest Hill Road Begins Spring 2024 Shore Drive Ongoing - Excavation Resumes Week of 8/26, Trenchless Scheduled for Week of 9/16
Curtis Street Excavated Work Complete, Trenchless Scheduled for Week of 9/2  Sterling Street Excavated Work Complete, Trenchless Scheduled for Week of 9/16
Dow Street Excavated Work Complete, Trenchless Scheduled for Week of 9/16 Upland Road Trenchless Scheduled for Week of 9/2
Endicott Avenue Trenchless Scheduled for Week of 9/16 Ware Street Trenchless Scheduled for Week of 9/16
Fairfax Street Ongoing - Excavation Resumes September 2024, Trenchless Scheduled for Week of 9/2 Waterhouse Street Trenchless Scheduled for Week of 9/2
Farragut Avenue Excavated Work Complete, Trenchless Scheduled for Week of 9/9 West Adams Street Complete August 2024
Gordon Street Complete August 2024 West Quincy Street Excavated Work Complete, Trenchless Scheduled for Week of 9/16
Hamilton Road Complete August 2024 Woodstock Street Trenchless Scheduled for Week of 9/9
Hardan Road Trenchless Scheduled for Week of 9/16 Victoria Street Trenchless Scheduled for Week of 9/2
High Street Trenchless Scheduled for Week of 9/16    


 

Image
Map showing the limits of work for sewer rehab in West Somerville

 

Schedule of Work

While all timelines are subject to change, substantial work is expected to begin in June 2024 and be completed by December 2024 with final paving for select streets in spring 2025. Daily work hours are approximately 7 a.m. to 4 p.m.


Anticipated Impacts

Streets and sidewalks are expected to remain open for the duration of the project. Lane closures, lane shifts, and parking restrictions may be implemented as needed. Driveway access will be maintained.

Excavation may generate moderate noise during work hours (typically between 7 a.m. and 4 p.m.) throughout the project area. Pipe lining may produce a bubblegum-like odor that will dissipate quickly once the process is complete.


Stay Informed

Residents in impacted areas will receive notification via flyers and community alerts prior to work starting in their area. 

Sign up for the City alert system to receive notifications about disruptive construction, snow emergencies, and major events planned for your neighborhood: somervillema.gov/alerts

Have questions? Email construction@somervillema.gov, call the Engineering Division at (617) 625-6600 ext. 5400, or call 311.


 

Programs & Initiatives

If you are a business, consultant, or non-profit that may be able to support Somerville’s business community, we encourage you to respond to our Request for Information (RFI).
Members will develop a recommendation to the Mayor on both the location and scope of a renovated or new school to meet the needs of the Winter Hill Community Innovation School and potentially the Benjamin G. Brown School.

Please submit website feedback using this form. Be sure to include:

A description of the issue (if any)
A link to the affected pages

Thank you for your feedback!